Quality Control System

Long experience of the plant for manufacture equipment for thermal power stations, pipelines of steam and hot water, pressure vessels, presence of appropriate equipment and qualified level of specialists guarantee high level of performance of works and services.

The quality of product produced by JSC Kharkov Boiler Mechanical Plant meets worldwide requirements and confirmed by the following certificates.

No

Sphere of application

Certificate No

Period of validity

remarks

1

Parts and elements of steam and hot water boilers, pipelines of steam and hot water

РРС 00-28903
(permition)

16.04.2013

 

2

Fittings and assembly units of pipelines of steam and hot water for thermal power plants (TPP)

РОСС UA.ГС02.Н00265

06.04.2011

 

3

Production of equipment operating under pressure in accordance with Directive 97/23/EC

07 202 3037 WZ 1715/07
 

07.2010

 

 

4

The manufacture of power engineering, in accordance with EN ISO 3834-3: 2005

UA-2007-046

25.07.2010

 

5

Steel construction. Production and certification, in accordance with the DIN 18800-09. Class D

G 884/2007

29.07.2010

 

6

Manual arc welding with coated electrode acc. to DIN EN ISO 4063-111

07 202 3637 Z 0137/7/D/009

Unlimited

Annual audit

7

Arc welding by metal electrode in active gasses (MAG), in accordance with DIN EN ISO 4063-135

07 202 3637 Z 0137/7/D/003

Unlimited

Annual audit

8

Arc welding by tungsten electrode in inert gases with filler wire and without it (TIG), in accordance with DIN EN ISO 4063-141

07 202 3637 Z 0137/7/D/010

Unlimited

Annual audit

9

Manual combined welding, in accordance with DIN EN ISO 4063 - 141/111

07 202 3637 Z 0137/7/D/001

Unlimited

Annual audit

10

Manual combined welding, in accordance with DIN EN ISO 4063- 141/135

07 202 3637 Z 0137/7/D/001

Unlimited

Annual audit

11

Design, manufacture and distribution of power engineering, in accordance with EN ISO 9001: 2000

In the execution stage

 

Prev. until 24.11.
2008

12

Arc welding with flux wire electrodes (WF), in accordance with DIN EN ISO 4063-121

In the execution stage


 

 

13

Arc welding flux cored wire with the protection of active gas (CFG), in accordance with DIN EN ISO 4063-136

In the execution stage

 

 

14

Elements of pipe heating surfaces, collectors of stationary steam, hot water boilers, heat-exchangers, including membrane and gas-tight units with the following parameters: Pwork. from 0,07 MPa to Rabbs. 37.27 MPa and T ≥ 145 ° C to 560 ° C.

In the execution stage

 

 


All products of the plant are certified in accordance with the Ukrainian national quality system UkrSEPRO and meet the requirements of DSTU ISO 9001-2001.

The plant developed and implemented a program of quality control of products.

Implemented methods of quality control:

  •   Visual and measuring.
  •   Ultrasound.
  •   Radiographic.
  •   Capillary.
  •   Mechanical testing.
  •   Metallographic studies.
  •   Hydraulic test (up to 1000 atm.)
  •   Steel scope.
  •   Measurement of hardness.

Plant Laboratories of metals and welding, performing quality control, equipped with all necessary equipment and qualified in the prescribed manner.

In the oxygen point of the plant organized sector of repair, testing and inspection of the oxygen and carbon dioxide cylinders

At the area of flame apparatus established a test laboratory for testing flame apparatus. The laboratory is accredited in UkrSEPRO system.